Commissioning Standard

Smart Citizens' methodology for validating and signing off every smart-home system before customer handover.

Executive summary

The essentials

  • Every project must be commissioned by a certified engineer
  • No handover without a signed commissioning report
  • Local-only operation is verified on every site
  • Every scene is executed and evidenced three times

Purpose

Ensure every Smart Citizens system behaves as designed under realistic conditions, with evidence that survives an audit years later.

Scope

All residential and light-commercial installations, including retrofits and developer handover projects.

Design principles

Principle 1

Evidence over opinion — every claim is backed by a captured artefact

Principle 2

Local-first — cloud is a convenience, not a dependency

Principle 3

Reproducible — every scene runs three times without deviation

Principle 4

Owner-witnessed — critical scenes are demonstrated to the owner

Engineering requirements

Engineering requirements

Mandatory requirements
  • Certified commissioning engineer on every site
  • Written commissioning plan issued before starting
  • Signed commissioning report at closure
  • Screenshots and logs archived to the customer portal
  • Sensor calibration recorded with timestamps

    Best practices

    Plan

    Plan: Publish the commissioning plan 48 h before mobilisation

    Sequence

    Sequence: Commission subsystem by subsystem, not room by room

    Witness

    Witness: Invite the owner for critical scene demos

    Archive

    Archive: Store all artefacts in the customer portal same-day

    Installation workflow

    Installation workflow

    Delivery

    How it works

    1. 1. Pre-check

      Confirm installation dossier is signed and every device is online.

    2. 2. Firmware baseline

      Verify each device matches the approved baseline for this site.

    3. 3. Naming audit

      Every device name matches the Smart Citizens naming convention.

    Configuration & programming workflow

    Configuration & programming workflow

    Delivery

    How it works

    1. 1. Import scenes

      Load the project scene set from the design tool.

    2. 2. Bind automations

      Attach automations to their trigger sources and confirm state paths.

    3. 3. Publish

      Push configuration to the site controller and verify sync.

    Commissioning steps

    Commissioning steps

    Delivery

    How it works

    1. 1. Scene execution

      Run every scene three times; capture logs and screenshots.

    2. 2. Sensor calibration

      Calibrate presence, lux and temperature sensors under occupancy.

    3. 3. Automation dry-run

      Trigger each automation manually to confirm expected behaviour.

    4. 4. Failover drill

      Disconnect WAN and primary gateway; verify local scenes still operate.

    5. 5. Load test

      Execute a Good Morning sequence and log actuation timings.

    Validation checklist

    Validation checklist

    Validation checklist (must do)
    • Every scene reproducible three times
    • All sensors calibrated with recorded values
    • Local operation confirmed with WAN disconnected
    • Alert paths tested for critical automations
    Common mistakes
    • Signing off without running a WAN-disconnect drill
    • Calibrating sensors on the bench instead of in place
    • Testing scenes only once
    • Skipping firmware verification

    Quality assurance checklist

    Report completeness

    Every commissioning report field is populated.

    Evidence archive

    Screenshots and logs stored in the customer portal.

    Owner sign-off

    Owner has witnessed and signed critical scene demos.

    Acceptance criteria

    Acceptance criteria
    FeatureTargetVerification methodPriority
    Scene reproducibility
    100% across 3 runsAutomated log reviewHigh
    Local-only operation
    PassWAN disconnect drillHigh
    Sensor calibration record
    One per sensorPortal checkMedium
    Acceptance criteria

    Risk matrix

    Risk matrix
    FeatureLikelihoodImpactMitigation
    Owner absent for handover
    MediumMediumReschedule; do not close project without witnessed sign-off
    Cloud-only feature marketed as local
    LowHighLocal-first tag on every scene; flagged in commissioning report
    Risk matrix

    Common mistakes & troubleshooting

    Troubleshooting tips

    Delivery

    How it works

    1. Scene deviates between runs

      Check for a competing automation triggered by an overlapping condition.

    2. Sensor false-trigger

      Re-calibrate under real occupancy; check for airflow or reflective interference.

    Documentation requirements

    Documentation requirements

    Documentation deliverables
    • Signed commissioning report
    • Sensor calibration log
    • Scene execution evidence
    • Failover drill evidence

      Maintenance timeline

      Maintenance timeline

      Delivery

      How it works

      1. Monthly

        Review remote health metrics and re-run critical scene tests.

      2. Quarterly

        Repeat failover drill; verify calibration drift.

      Version & change log

      Version 1.0

      Approval status: Approved · Effective date: 2026-01-15 · Last revision: 2026-07-08

      Author / Reviewer

      Author: Smart Citizens Engineering · Reviewer: Dr. Ashraf Nouri

      Change log

      v1.0 — 2026-07-08

      Initial published edition. (Smart Citizens Engineering)

      Frequently asked questions

      FAQ

      Frequently asked questions

      How long does commissioning take?

      A typical villa takes 1–3 days depending on scene count and subsystem breadth.

      Can commissioning happen remotely?

      Some checks can be remote, but WAN-disconnect drills and owner sign-off must be on-site.

      Official citation
      How to cite
      Suggested citation
      Smart Citizens Engineering. "Commissioning Standard." Smart Citizens, 2026-01-15. https://ai.smartcitizens.ae/standards/commissioning-standard.
      Smart Citizens Engineering (2026). Commissioning Standard. Smart Citizens. Retrieved 2026-07-23, from https://ai.smartcitizens.ae/standards/commissioning-standard
      CategoryEngineering Standard
      AuthorSmart Citizens Engineering
      PublisherSmart Citizens
      Published2026-01-15
      Last updated2026-07-08
      VersionPlaceholder-ready
      Language
      en
      LicenseCC BY-NC 4.0 (unless noted)
      DOIPlaceholder-ready